土工膜施工注意事项:
Precautions for Geomembrane Construction:
1、电器设备、电源线路应符合有关专业规范要求。
1. Electrical equipment and power lines should comply with relevant professional specifications.
2、热风枪、砂轮机和焊机拖带的电源线在使用过程中,必须最大限度的远离其工作部位,以免损伤脑筋电线发生漏电。
2. During use, the power cords of hot air guns, grinding machines, and welding machines must be kept as far away from their working areas as possible to avoid damaging the brain and causing electrical leakage.
3、除热风焊接外,热风枪的嘴部在任何情况下都不得与HDPE膜面接触,并且尽可能的远离膜面、人体、机械等物体。
3. Except for hot air welding, the mouth of the hot air gun must not come into contact with the HDPE film surface under any circumstances, and should be kept as far away from objects such as the film surface, human body, and machinery as possible.
4、焊机在不使用时,不得直接放置在HDPE膜面上,应放置在支架或沙袋带上。
4. When the welding machine is not in use, it should not be placed directly on the HDPE film surface, but on a bracket or sandbag belt.
5、裁膜刀使用完毕后,应立即将刀片收回刀盒内。
5. After using the film cutting knife, the blade should be immediately retracted into the knife box.
6、在现场使用的各种临时性小型工具,使用完毕,应及时放入工具箱内。
6. All temporary small tools used on site should be promptly placed in the toolbox after use.
7、严禁将从挤压焊接机枪头摘下的焊料物直接丢弃在土工膜面上。
7. It is strictly prohibited to discard the solder removed from the extrusion welding machine gun directly on the surface of the geomembrane.
8、凡在陡坡边缘等危险场所作业时,必须佩带安全带,必须带安全帽。
8. When working in hazardous areas such as steep slope edges, safety belts and helmets must be worn.
9、HDPE土工膜施工现场禁止吸烟,还应配备消防设施,不得穿带铁钉的鞋或高跟硬底鞋到膜面上行走,不允许从事有可能破坏土工膜成品的一切活动。
9. Smoking is prohibited on the construction site of HDPE geomembrane, and fire-fighting facilities should be equipped. Shoes with iron nails or high heels with hard soles are not allowed to walk on the membrane surface, and all activities that may damage the finished geomembrane are not allowed.